Feasibility Study completed
Geophysical and Geotechnical investigation completed
Initial Environmental Examination (IEE) study report approved
Detail Engineering Design substantially completed and preparation of construction drawings ongoing concurrently
Sediment sampling and laboratory analysis completed
Physical modeling and Numerical modeling of Headworks structures completed and preparation of report ongoing
All the site facilitating works including the construction and upgradation of infrastructures completed
33kV transmission line for construction power supply completed
Civil works contractor mobilization commenced in January 2020; Construction works advancing from different work fronts
Diversion tunnel completed and river diversion commenced
Adit-1 and Adit-2 Tunnel completed whereas excavation works of Adit-3 in progress
Excavation of Headrace Tunnel ongoing from Adit-1 and Adit-2
Excavation of powerhouse main access tunnel in final stage
Excavation of upper pressure tunnel in progress
Detail Design of Transmission line for power evacuation completed, tender document preparation for the construction of transmission line in progress
Bidding process for the award of contract for hydromechanical works in final stage; contract to be awarded by the end of October 2021
Bidding process for the award of contract for electromechanical works in final stage; contract to be awarded by the end of October 2021