PPA Signed for Siwa Khola HPP
On August 5, 2022, Mewa Developers signed Power Purchase Agreement signed with Nepal Electricity Authority for Siwa Khola Hydropower Project.
Powerhouse Cavern Excavation Completion
Middle Mewa HPP achieved a key breakthrough on Sep 17, 2022 with the excavation completion of powerhouse cavern. Such powerhouse is one of very few in Nepal.
Construction Embarkment for Middle Mewa HPP
The project embarked on construction in January 2020 after the award of civil works contract to CE construction.
Generation License obtained for Middle Mewa HPP
In January 2020, Generation License was obtained from the Department of Electricity Development for Middle Mewa HPP.
PPA Signed for Middle Mewa HPP
In August 2018, Mewa Developers signed Power Purchase Agreement was signed with Nepal Electricity Authority for Middle Mewa Hydropower Project.
Mewa Developers Established
The company was incorporated as a private company on July 8, 2016, and was converted to a public company on June 23, 2021.