Siwa Khola Hydropower Project

Project in brief

Located at a distance of 730 km north-east of Kathmandu, Siwa Khola HPP is one of the very few Peaking Run of River (PROR) type projects in Nepal. The project is proposed in Siwa river in Taplejung District, Koshi Province of eastern Nepal. The headworks is proposed on the left bank of Siwa river and powerhouse on right bank of Mewa river between elevation of 1629.51 m and 1452 m above mean sea level. 

Progress Updates

Survey License obtained For 9.3 MW.

Power Purchase Agreement for 9.3 MW signed with NEA 

Generation license obtained

Initial Environment Examination (IEE) study has been approved for 9.3 MW

Financial closure signed completed

 Approval for Generation license in the final stage

Initial Environment Examination (IEE) study has been approved for 9.3 MW

Detailed Engineering Design Substantially completed

Geophysical Investigation works completed

11 kV pole installation works for construction power ongoing

Track opening of Access Road for Headworks ongoing

Lowa Khola RCC bridge construction ongoing

Design of bailey bridges on Headworks and powerhouse completed; Construction of Abutments Ongoing

  • Civil works contract award and signing at final stages

Gallery